Construction of Road Employer: Guinea Roads Authority Funded by: Government of Guinea
Project Title: Construction Works of Transversal Roads (T12, T13, T14)
Client: Ministry of Infrastructure and Public Works
Consultant: Administration and Control of Major Projects (ACGP)
Contractor: PAVIFORT AL-ASSOCIATES SA.
Start Date: October 03, 2024
Duration: 1,095 Calendar Days
Completion Date: October 02, 2027
Contract Value: USD 135,069,392
Total Road Length: 15.36 km
CURRENT PROJECT PROGRESS (T13 SECTION)
• Clearing, grubbing, and topsoil removal completed (km 0+000 to 6+400)
• Earthwork’s excavation ongoing (km 0+000 to 6+400)
• Earthworks substantially completed (km 0+200 to 4+100)
• Drainage excavation completed (km 0+200 to 3+600)
• Over 3000 meters prepared for U-Ditch concrete works (ongoing)
• 4 Box Culvert 100% Completed and 6 Box Culvert on Progress
• 1 Bridge Construction on Progress